Alicante continues to modernize 14 educational institutions: 11 applications from construction companies have been submitted
🔧 14 schools and a kindergarten will be renovated as part of a municipal plan
Alicante, 4 June 2025 - As part of the municipal plan to modernise the education infrastructure in Alicante , renovation and construction work will be carried out in 14 educational institutions in the city. On Wednesday, at a meeting of the procurement committee , it was revealed that 11 construction companies had submitted their bids to participate in the competition.
📌 The total budget of the project was 466,168 euros and includes work in 13 primary schools and one kindergarten :
Benalúa, Gloria Fuertes, Nou d'Octubre, La Aneja, Voramar, Rafael Altamira, Enric Valor, San Blas, Ramón Llull, Santa Faz, Gabriel Miró, Florida, Óscar Esplá and EI Tossalet.
💬 Quotes from city authorities
👷♀️ Cristina Garcia , Infrastructure Advisor:
"We continue to implement the educational infrastructure maintenance plan , renovating institutions and meeting their urgent needs. It is gratifying to see such interest from construction companies."
👩🏫 Maricarmen de España , Education Advisor:
" Improving Alicante's educational institutions is our priority . We have already doubled the budget for this purpose to 1.2 million euros . And this is just the beginning - in collaboration with the Generalitat, we are developing projects including new schools (College 56, La Almadraba) and major renovations in five institutes."
🏗️ Companies that applied:
- Escapes and Hijos SL
- Inelsa Ingeniería Infraestructuras SL
- Benacantil del Levante SL
- Rocace SL Constructions
- Villanto Constructions SA
- Niberma Group S.L.
- Play and Flex SL
- Construcciones Rafael Zarzoso SL
- Alitek Ingeniería y Pavimentos SL
- Evealia Levante SL
- Nerco Infrastructures S.L.
🛠️ Work plan: 13 lots - 14 objects
🏫 Schools:
1️⃣ CEIP Benalúa - repair of pavement and playground (90 days)
2️⃣ CEIP Gloria Fuertes - modernization of the ramp to the children's yard (90 days)
3️⃣ CEIP Nou d'Octubre - interior painting works (75 days)
4️⃣ CEIP La Aneja – Restoration of load-bearing beams in the basement (60 days)
5️⃣ CEIP Voramar - installation of a ramp on an internal staircase (90 days)
6️⃣ CEIP Rafael Altamira - access to children's classrooms from the yard (60 days)
7️⃣ CEIP Enric Valor - roof and gutter repair (32 days)
8️⃣ CEIP San Blas — development of a children's yard (60 days)
9️⃣ CEIP Ramón Llull and CEIP Santa Faz – Security premises renovation (30 days)
🔟 CEIP Gabriel Miró - Adaptation of the entrance for people with disabilities (60 days)
1️⃣1️⃣ CEIP Florida - Window and Door Lintel Repair (30 days)
1️⃣3️⃣ CEIP Óscar Esplá - cornice repair (30 days)
🧒 Kindergarten:
1️⃣2️⃣ El Tossalet - Warehouse conversion into a restroom (30 days)
🛠️ This large-scale project will not only improve the condition of the buildings, but will also increase the quality and comfort of the educational process for thousands of students in Alicante.
📢 Stay tuned for updates - the city will continue to invest in modern and accessible education !